Progress Invoicing & Cash Flow
How do I fill out a construction pay application (G702/G703)?
A pay application has two parts. The continuation sheet (AIA G703, or a form laid out like it) lists every line of your schedule of values and how much of each is complete. The application itself (G702) is the one-page summary that turns those totals into the amount due. Fill out the continuation sheet first, then carry its totals to the summary.
Part one: the continuation sheet
One row per line of your schedule of values, with these columns:
- A. Item number.
- B. Description of work.
- C. Scheduled value. The dollar value of the line. It does not change during the job.
- D. Work completed, from previous applications. Carried over from last month's total.
- E. Work completed, this period. What you did since the last application.
- F. Materials presently stored. Material delivered and not yet installed, if your contract allows billing for it.
- G. Total completed and stored to date. D + E + F, and the percentage of the scheduled value that represents.
- H. Balance to finish. C − G.
- I. Retainage. The amount held on this line, if it is tracked by line.
Work one row at a time. Decide the percent complete to date, multiply by the scheduled value to get the total, and subtract column D to get this period. Working from the total to date keeps small errors from piling up month after month.
Part two: the summary
- Original contract sum.
- Net change by change orders. Approved ones only.
- Contract sum to date. Line 1 plus line 2.
- Total completed and stored to date. The total of column G.
- Retainage. The percentage in your contract, applied to completed work and to stored material.
- Total earned less retainage. Line 4 minus line 5.
- Less previous certificates for payment. Line 6 from your last application.
- Current payment due. Line 6 minus line 7.
- Balance to finish, including retainage. Line 3 minus line 6.
A worked example
- Original contract sum: $200,000
- Approved change orders: $10,000
- Contract sum to date: $210,000
- Total completed and stored to date: $120,000
- Retainage at 10 percent: $12,000
- Total earned less retainage: $108,000
- Less previous certificates: $72,000
- Current payment due: $36,000
- Balance to finish, including retainage: $102,000
Why applications get rejected
- Column D does not match last month's column G. The most common error. Every application starts where the last one ended.
- A line billed past 100 percent. Extra work belongs on a change order line.
- Unapproved change orders included.
- Scheduled values changed without an approved revision.
- Retainage at the wrong rate, or left off stored materials.
- Missing signature or notarization where the contract requires it.
- Missing attachments: lien waivers, certified payroll, stored material invoices.
- Submitted after the cutoff.
Any one of these can push payment to the next cycle.
Before you send it
- The scheduled values still add up to the contract sum to date.
- Every row: D + E + F = G, and no G is larger than C.
- Line 7 equals line 6 of the previous application.
- The percentages match what the superintendent would say on a walk.
- The waivers cover the right amounts and the right dates.
If the GC accepts a pencil copy, send one a few days early. Agreeing the percentages before the formal copy is the fastest way to be paid on time.
Where ConstructStream fits
ConstructStream prints a Contractor's Application for Payment with its continuation sheet from the job's own numbers: the lines of the accepted bid, approved change orders as their own lines, what earlier invoices billed, and the retainage held. The previous-application column is carried forward, not retyped, so the error that sends most applications back does not happen.